An accessory dwelling unit (ADU) is a second home on a lot with a house or apartment building: attached, detached, or built inside a garage or other existing space. In Los Angeles County, most of the rules for one are written in Sacramento. State law sets the most a city or the county can ask, and a local rule that goes further doesn't hold.
The law moved to Government Code sections 66310 and following in 2024, and several 2025 bills changed it again, most of them effective January 1, 2026. Everything below is current as of November 2026.
What counts as an ADU or a JADU
An ADU has complete, independent living facilities: a place to live, sleep, eat, cook and bathe, on the same lot as a primary home. A junior ADU (JADU) is smaller: no more than 500 square feet of interior livable space, built inside a single-family home. It needs its own entrance, an efficiency kitchen and a recorded deed restriction. Since January 1, 2026, the owner has to live on the property only if the JADU shares the house's bathroom.
On a single-family lot, the city or county has to approve these by right:
- one ADU and one JADU inside the existing or proposed house, or inside an existing accessory structure, with up to 150 square feet added for a way in and out;
- one new detached ADU with four-foot side and rear setbacks, which the city may cap at 800 square feet;
- any combination of the two, a point SB 543 made explicit from January 2026.
Sizes, height and setbacks
A detached ADU can be up to 1,200 square feet. An attached one can't exceed half the floor area of the existing house. A city may set its own maximum, but not below 850 square feet of interior livable space, or 1,000 square feet for a unit with more than one bedroom. Whatever its lot coverage, floor area or open space rules say, it has to allow an 800-square-foot ADU with four-foot side and rear setbacks.
A new ADU can't be held to setbacks over four feet from the side and rear lines, and converting existing space, or rebuilding in the same footprint, needs none.
Height: at least 16 feet for a detached ADU, or 18 feet within a half-mile walk of major transit, plus two feet to match the main roof's pitch. An attached ADU can reach 25 feet or the zone's limit for the house, whichever is lower.
Parking is capped at one space per unit or per bedroom, whichever is less. A garage torn down or converted for the ADU doesn't have to be replaced. Fire sprinklers aren't required in the ADU if the main house doesn't need them. The city can't require you to live on the property for an ADU, though it can require rentals of 30 days or more.
The review clock
The permit is ministerial: checked against objective standards, with no hearing. Since January 1, 2026, the permitting agency has 15 business days to say whether an application is complete. If it isn't, the agency has to list every missing item and can't add new ones on the next round. If it misses the deadline, the application counts as complete.
With a house already on the lot, the agency then has 60 days from a complete application to approve or deny; if it does neither, the ADU is deemed approved. A denial has to list what to fix, and you can appeal. An ADU filed with a new house can wait for the house decision.
One more timing rule: the ADU can't get its certificate of occupancy before the main house does. The exception: a detached ADU that has passed its inspections, in a county under a Governor's emergency proclamation made on or after February 1, 2025, where the house was destroyed.
Fees
No impact fees can be charged on an ADU with 750 square feet of interior livable space or less, or on a JADU of 500 square feet or less. Above 750 square feet, impact fees have to be proportional to the size of the main house. Utility connection fees are a separate matter: a unit built inside the existing house or an accessory structure can't be made to take a new, separate connection, while other ADUs can, at a fee proportional to their size or plumbing fixtures. Plan check and permit fees still apply.
Units built without permits
If your lot has a converted garage or back unit that was never permitted, the law now offers a path. Under Government Code 66311.7 (numbered 66332 until this year, from AB 2533), a city can't deny a permit for an unpermitted ADU or JADU built before January 1, 2020 because it misses today's building or ADU standards. The exception is work needed to fix conditions that make a building substandard under Health and Safety Code 17920.3. Impact fees and connection charges don't apply unless new utility work is needed, and owners may get a confidential code inspection from a licensed contractor before applying.
LA County Public Works runs a legalization process for these units, with sign-offs from agencies such as Fire, Regional Planning and Public Health, and Regional Planning may waive zoning violations for a unit built and occupied before 2020.
How it runs in LA County, Glendora and Pasadena
The 2025 California building codes apply to permit applications filed on or after January 1, 2026, and pre-approved plans drawn to the old codes expired with them.
- Unincorporated LA County: applications go through EPIC-LA. The County's free pre-approved plans (two at 1,200 square feet, one at 800) can be turned or mirrored but not changed, and each still needs a Regional Planning plot plan, Title 24 energy calculations and the referral agencies' sign-offs. Regional Planning's archived page says those pre-approvals ran through December 31, 2025, so ask whether a set has been reissued under the 2025 codes. The County is also updating its ADU ordinance.
- Glendora: applications go through the city's Civic Access portal, and the ADU standards are in Municipal Code section 21.04.040. The city lists two pre-approved designs from private firms, 400 and 495 square feet. Its submittal list asks for a soils report on hillside lots, and a detached ADU skips fire sprinklers only if, among other conditions, the lot is outside a fire hazard severity zone.
- Pasadena: the city's free standard plans expired on December 31, 2025. A studio plan updated to the 2025 code was posted in August 2026; the older plans now serve only homes red-tagged after the Eaton Fire.
Where we come in
We build ADUs and room additions across Glendora, Pasadena and the rest of LA County. We walk the lot first, find the permits and reviews the project needs, bring in the architects and engineers it calls for, and price the work task by task. Sloped lots add steps of their own (building on a hillside lot), and the ADUs and additions page has the rest.
Sources
- Government Code 66313: definitions California Legislative Information.
- Government Code 66314: ADU standards California Legislative Information.
- Government Code 66317: ministerial review and timelines California Legislative Information.
- Government Code 66321: size and height limits California Legislative Information.
- Government Code 66323: units approved by right California Legislative Information.
- Government Code 66328: certificate of occupancy California Legislative Information.
- Government Code 66333: junior ADUs California Legislative Information.
- SB 543 (2025), chaptered text: fees and unpermitted units California Legislative Information.
- 2025 California Building Standards Code, Information Bulletin 25-01 California Building Standards Commission.
- Pre-Approved ADU Standard Plans Program Los Angeles County Public Works.
- AB 2533 frequently asked questions Los Angeles County Public Works, Building and Safety.
- Accessory Dwelling Units and SB 9 City of Glendora.
- ADU Standard Plans Program City of Pasadena.